Construction Projects

Construction Projects

Project Updates – 6-11-2024

PK-013 Rectangular Rapid Flashing Beacons (RRFB) & Trail Extensions

Current Status: In Design/Review

Contractor: To Be Determined (TBD)

Project Area:

  • RRFB – TH59 and A Street
  • Trail Extension – Boyer Street to Windstar Street
  • RRFB and Trail Extension – County Road 7

Project Overview:

  • RRFB - TH59 and A Street – Reconstruction of the curb ramps and curb on the northwest half of the intersection. The curb will be bumped out and new RRFBs will be installed.
  • Trail Extension – Boyer Street to Windstar Street – Construction of an approximately 550’ of new 10’ wide concrete trail with some minimal site grading and restoration.
  • RRFB and Trail Extension – County Road 7 – Construction of approximately 800’ of new 10’ wide concrete trail following the alignment the levee. Removal of portions of the existing trail, Installation of the RRFBs at the new crossing of County Road 7 and with some minimal site grading and restoration.

 

PK-015 Independence Park Parking Lot

Current Status: The storm sewer, subgrade excavation, subdrain, fabric and gravel work has been completed. Concrete work to start the third week in June. 

Contractor: Towne & Country Excavating, LLC - Garvin, MN

Project Area: Access road and parking lot on the west side of Independence Park.

Project Overview: Existing access, posts, and parking lot to be replaced with a new concrete surface, curb & gutter, and storm sewer

ST-001-2024 Chip Seal Project

Current Status: Project has been awarded.

Contractor: Pearson Bros., Inc. - Hanover, MN

Project Area: The following streets are included in the project:

  • Channel Parkway - TH19 to TH59
  • Susan Drive - Clarice Ave to 400ft NE of TH59
  • Tiger Drive - TH23 to 400ft N of Victory Dr
  • Soucy Drive - 6th St to End
  • Fremont Street - Ranch Ave to Pleasant St
  • Pleasant Street - 6th St to End
  • Ranch Avenue - Soucy Dr to End
  • Winifred Circle - Soucy Dr to End
  • 5th Street - Main St to Marshall St
  • Redwood Street - 5th St to 7th St
  • Lyon Street - 5th St to 6th St
  • Commencement Boulevard - TH23 to Tiger Dr

Project Overview: Our contractor will post no parking signs along the boulevard, this will allow them to street sweep the entre street surface to ensure proper adhesion with the chip seal oil, the street surface and the granite chips that are being applied.

ST-002-2024 Overlay Project

Current Status: The ADA ramps, curb replacement and site restoration have been completed. Milling is anticipated to start June 10th with paving to follow.

Contractor: Central Specialties, Inc. - Alexandria, MN

Project Area: The following streets are included in the project:

  • O'Connell St - Service Road to Birch St
  • Peltier/Glen/Simmons
  • Rainbow Drive - Madrid St to RR Tracks
  • Floyd Wild Drive - Susan Dr to Canoga Park Dr
  • Canoga Park Drive - TH23 to Canoga Circle Seam
  • Market Street - E. College Dr to Mall Parking Lot
  • Whitney Street - E. College Dr to N. 4th St
  • Poplar Avenue - N. Whitney St to N. Hill St
  • Boyer Drive - TH59 to Margaret Ave

Project Overview: Repair/replace curb and gutter, install ADA pedestrian ramps, mill, and overlay entre existing asphalt surface, installing new traffic striping.

ST-007 UCAP Bus Shelters

Current Status: In Design/Review

Contractor: TBD

Project Area:

  • North 4th Street and Darlene
  • Riverview Court Apartments
  • Camden Drive
  • Freedom Park
  • Dogwood Avenue
  • Susan Drive and Baseline Road (2)

Project Overview: This project includes a minimal site and sidewalk work on preparation of the footing and bus shelter structures.

ST-009 Addison Parking Lot

Current Status: Construction has been completed and open to traffic.

Contractor: R&G Construction Co. - Marshall, MN

Project Area: This project is in the west quadrant of the intersection of W Lyon Street and E College Drive.

Project Overview: The project removed the existing surfacing and repaved the parking lot.

ST-010 Lyon Circle

Current Status: The Pre-construction meeting has been held and construction is anticipated to start the week on June 17th weather dependent.

Contractor: A&C Excating, LLC – Marshall, MN

Project Area: South of E Lyon Street.

Project Overview: This project includes installation of new storm sewer, sanitary sewer curb and gutter with bituminous surfacing and concrete driveways.

ST-012-2024 South Whitney Street 

Current Status: Watermain and sanitary sewer have been installed between E. College Drive and E. Marshall Street. The contractor is currently working on water and sewer services, once these are complete they will move to storm sewer in the same two blocks.

Contractor: D&G Excavating, Inc., Marshall, MN 

Project Area: South Whitney Street starting at Ease College Drive to Jean Street, excluding the intersection Marshall Street and South Whitney Street. 

Project Overview: This project includes removal of the existing facilities and installation of a new storm sewer, sanitary sewer, watermain, concrete driveways, sidewalk, curb & gutter, bituminous surface, and site restoration.

SWM-009 Canoga Pond

Current Status: In Design/Review

Contractor: TBD

Project Area: The outlet pipe is located on the NE edge of the pond. The pond is NE of Canoga Park Drive.

Project Overview: This project will remove/replace the pond existing outlet pipe.