Construction Projects

Construction Projects


Project ST-003
S. 1st St./Greeley St./Williams St. Reconstruction Project
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
May 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of S. 1st Street between George St. and Greeley St., Greeley Street
between W. College Dr. and Saratoga St., and Williams Street between George St. and Maple St. Work
will include replacement of Sanitary Sewer, Watermain, Storm Sewer Catch Basins, Grading, Curb and
Gutter, Sidewalk, Asphalt Paving and other miscellaneous work. 
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 
Click Here to View the Informational Meeting Powerpoint Presentation
Click Here to View the Project's StoryMap that includes information regarding the project.
Click Here to Provide Comments about the project.

Project ST-004
Halbur Road Reconstruction Project
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
May 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of Halbur Road between Michigan Ave. and Erie Rd. (Co. Rd. 33). Work
will include replacement of Sanitary Sewer, Storm Sewer Catch Basins, Grading, Curb and Gutter,
Sidewalk, Concrete Paving and other miscellaneous work. 
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 
Click Here to View the Informational Meeting Powerpoint Presentation
Click Here to View the Project's StoryMap that includes information regarding the project.
Click Here to Provide Comments about the project.

Project ST-005
Rose/Addison Parking Lot Reconstruction Project
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
May 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of the Rose and Addison downtown city parking lots adjacent to W.
Lyon Street. Work will include Grading, Curb and Gutter, Sidewalk, Concrete Paving and other
miscellaneous work. 
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 

Project ST-006
Safe Routes to School (SRTS) School Pedestrian Crossing Improvements Project
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
June 2022 (anticipated)      -     Anticipated Completion: August 2022
Project Details:
Construction of pedestrian crossing enhancements and associated signage. Work will
include construction of ADA-compliant pedestrian ramps and sidewalk, raised pedestrian refuge islands,
installation of Rectangular Rapid Flashing Beacon (RRFB) signage, Dynamic Speed Feedback & School
Zone Speed Limit signage and other miscellaneous work. This project is mainly funded through a grant
received from MnDOT.
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 

Project ST-007
2022 UCAP Bus Shelter Construction Project
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
May 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Construction and installation of several bus stop shelter pads and structures located
at various UCAP-operated bus shelter locations throughout the City of Marshall. Work will include
Grading, Curb and Gutter, Sidewalk, Concrete Paving, Bus Shelter Foundation and Assembly, and other
miscellaneous work. This project is mainly funded through a grant received by UCAP from MnDOT.
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 

Project SWM-002
Legion Field Stormwater Improvements (Phase II) Project - Parkway Basin
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
May 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of S. 1st Street between George St. and Greeley St., Greeley Street
between W. College Dr. and Saratoga St., and Williams Street between George St. and Maple St. Work
will include replacement of Sanitary Sewer, Watermain, Storm Sewer Catch Basins, Grading, Curb and
Gutter, Sidewalk, Asphalt Paving and other miscellaneous work. 
Latest Update:
December 22th, 2021 - Bolton & Menk is assisting City Engineering staff on developing
plans for this project. 


Project PK-001
Independence Park Trail Replacement Project
Bid Award Date:
August 25th, 2021     -     Prime Contractor: A & C Excavating, Marshall, MN
Construction Begin: September 16, 2021     -     Anticipated Completion: July, 2022
Project Details: Replacement of the existing trails throughout Independence Park including
the area around the baseball field area.

Latest Update: December 22nd, 2021 - A&C Excavating has completed replacement of much
of the trail in the vicinity of the baseball fields, basketball court and horseshoe pits. Remaining
trails will be removed and reconstructed in spring and early summer of 2022.


Project SWM-007
Independence Park Pond Forebay Expansion Project
Bid Award Date:
October 18th, 2021     -     Prime Contractor: Towne & Country Excavating, Garvin, MN
Construction Begin: April, 2022 (Anticipated)     -     Anticipated Completion: July, 2022
Project Details: Excavation and expansion of the pond forebay at the south end of Independence
Park including pipe culvert and new concrete trail. 

Latest Update: December 22nd, 2021 - This project has been awarded to Towne & Country Excavating.
Work is expected to begin in spring of 2022. 


Project Z87
Diversion Channel Slope Repair and Sheet Pile Removal Project
Bid Award Date:
September 14th, 2021     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: April, 2022 (Anticipated)     -     Completion: October 2022
Project Details: Grading and slope correction of washout areas of the Redwood River Diversion
Channel. Also includes removal of sheet piling and storm water outfall repairs. 

Latest Update: December 22nd, 2021 - R&G Construction is expected to complete this work
during 2022.

Project ST-002-2022
2022 Bituminous Overlay and Pedestrian Ramp Improvements Project
Expected Advertisement:
January 2022     -     Prime Contractor: TBD
Construction Begin:
May 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.  

Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 

Project ST-001-2022

2022 Bituminous Chip Sealing Project
Expected Advertisement: January 2022     -     Prime Contractor: TBD
Construction Begin:
June 2022 (anticipated)      -     Anticipated Completion: August 2022
Project Details:
Chip sealing on city streets at various locations within the City of Marshall. 
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project.