Construction Projects

Construction Projects


Project Z82
N. 1st St./W. Redwood St./W. Marshall St. Reconstruction Project
Bid Award Date: February 9th, 2021     -     Prime Contractor: D & G Excavating, Inc., Marshall, MN
Construction Begin: April 26, 2021      -     Anticipated Completion: September 2021
Project Details: Reconstruction of N. 1st Street from E. Main St. to W. Marshall St., W. Redwood Street
from N. 1st St. to E. College Dr. and W. Marshall Street from N. 1st St. to E. College Dr. Work will
include replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk,
Asphalt Paving and other
miscellaneous work.
Latest Update: September 17th, 2021 - D&G has completed construction and final seeding on the project.
Minor cleanup items remain before this project will be closed. 

Click Here to view some project photos
Click Here to download the Project Z82 Newsletter
Click Here to download the Project Z82 Pre-Construction Meeting Notes from 4/21/2021

Project Z83
James Ave./Camden Dr. Reconstruction Project
Bid Award Date: February 23rd, 2021     -     Prime Contractor: Kuechle Underground, Inc., Kimball, MN
Construction Begin: May 24th, 2021      -     Anticipated Completion: September 2021
Project Details: Reconstruction of James Avenue between S. 4th St. and Camden Dr. and Camden Drive
between James Ave. and S. 4th St. Work will include replacement of Sanitary Sewer,
Watermain, Storm
Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
This project will also include replacement of the Storm Sewer main across Country Club Drive, through
the Marshall Golf Course to the outfall into the Redwood River.
Latest Update:
September 30th, 2021 - Kuechle has completed construction and final seeding on the
project. Final turf establishment and minor cleanup items remain. 

Click Here to view some project photos
Click Here to download the Project Z83 Newsletter


Project Z80
T.H. 23/Independence Park Sewer Realignment Project
Expected Advertisement: May 2021     -     Prime Contractor: D&G Excavating, Marshall, MN
Construction Begin: August 2021 (anticipated)      -     Anticipated Completion: September 2021
Project Details: Construction of Sanitary Sewer and Storm Water improvements adjacent to Highway
23 including relocation of Sanitary Sewer to Nwakama Street and
other miscellaneous work.
Latest Update: September 30th, 2021 - D&G has completed construction on this project.

Project Z88
2021 State Aid Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date:
April 13th, 2021     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: June 14th, 2021      -     Completion: September 2021
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: September 30th, 2021 - Duininck has completed overlays on all routes in this project.
Minor work remains to be completed.  

Click Here to view some project photos
Click Here to download the Project Z88 Newsletter


Project PK-001
Independence Park Trail Replacement Project
Bid Award Date:
August 25th, 2021     -     Prime Contractor: A & C Excavating, Marshall, MN
Construction Begin: September 16, 2021     -     Anticipated Completion: July, 2022
Project Details: Replacement of the existing trails throughout Independence Park including
the area around the baseball field area.

Latest Update: September 30th, 2021 - A&C Excavating has begun removing the existing trail and
paved area in the vicinity of the baseball fields, basketball court and horseshoe pits. Concrete is
being placed as the area is prepared. Fall work is expected to continue as weather permits.
Remaining work will be completed in 2022.


Project SWM-007
Independence Park Pond Forebay Expansion Project
Bid Award Date:
October 12th, 2021 (Anticipated)     -     Prime Contractor: TBD
Construction Begin: October, 2021 (Anticipated)     -     Anticipated Completion: July, 2022
Project Details: Excavation and expansion of the pond forebay at the south end of Independence
Park including pipe culvert and new concrete trail. 

Latest Update: September 17th, 2021 - This project is currently advertising. Bids are expected to
be opened on October 6th at 10 a.m.


Project Z84
Legion Field Park River Stabilization Project
Bid Award Date:
August 10th, 2021     -     Prime Contractor: A & C Excavating, Marshall, MN
Construction Begin: August 19, 2021     -     Completion: September 24, 2021
Project Details: Grading and riprap stabilization of the Redwood River riverbank adjacent
to the park shelter in the southwest portion of Legion Field Park. 

Latest Update: September 30th, 2021 - A&C Excavating has completed work on this project.

Project Z87
Diversion Channel Slope Repair and Sheet Pile Removal Project
Bid Award Date:
September 14th, 2021     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: October, 2021 (Anticipated)     -     Completion: October 2022
Project Details: Grading and slope correction of washout areas of the Redwood River Diversion
Channel. Also includes removal of sheet piling and storm water outfall repairs. 

Latest Update: September 30th, 2021 - R&G Construction is expected to complete this work
during the fall of 2021, weather permitting.

Project Z51
2021 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date:
February 23rd, 2021     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 3rd, 2021     -     Completion: June 17th, 2021
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: July 1st, 2021 - Duininck has completed the construction on this project. Some
turf re-establishment remains before this project will be closed.

Click Here to view some project photos
Click Here to download the Project Z51 Newsletter

Project Z50

2021 Bituminous Chip Sealing Project
Bid Award Date: March 9th, 2021     -     Prime Contractor: Asphalt Preservation Company Inc., Detroit Lakes, MN
Construction Begin: June 8th, 2021     -     Completion: June 14th, 2021
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: June 21st, 2021 - Asphalt Preservation has completed the work on this project.

Project Z78
Storm Structure Outfall Improvements Project
Bid Award Date:
April 13th, 2021     -     Prime Contractor: R & G Construction Co., Marshall, MN
Construction Begin: May 2021     -     Completion: May 18th, 2021
Project Details: Installation of two storm sewer manholes adjacent to Saratoga Street and the
Redwood River Diversion Channel. 
Latest Update: May 19th, 2021 - R & G Construction has completed the installation of the two
manholes on this project.

MERIT Center Pond Outfall Improvements
Bid Award Date: September 8th, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: April 2021     -     Completion: May 7th, 2021
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.
Latest Update: May 12th, 2021 - Towne & Country has completed the work on this project.