Construction Projects

Construction Projects


Project Z82
N. 1st St./W. Redwood St./W. Marshall St. Reconstruction Project
Bid Award Date: February 9th, 2021     -     Prime Contractor: D & G Excavating, Inc., Marshall, MN
Construction Begin: May 2021 (anticipated)      -     Anticipated Completion: September 2021
Project Details: Reconstruction of N. 1st Street from E. Main St. to W. Marshall St., W. Redwood Street
from N. 1st St. to E. College Dr. and W. Marshall Street from N. 1st St. to E. College Dr. Work will
include replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk,
Asphalt Paving and other
miscellaneous work.
Latest Update: March 29th, 2021 - City staff and the contractor will be scheduling a kick off meeting
with utilities, adjacent residents and businesses along these routes in the coming weeks.

Click Here to download the Project Z82 Newsletter

Project Z83
James Ave./Camden Dr. Reconstruction Project
Bid Award Date: February 23rd, 2021     -     Prime Contractor: Kuechle Underground, Inc., Kimball, MN
Construction Begin: June 2021 (anticipated)      -     Anticipated Completion: September 2021
Project Details: Reconstruction of James Avenue between S. 4th St. and Camden Dr. and Camden Drive
between James Ave. and S. 4th St. Work will include replacement of Sanitary Sewer,
Watermain, Storm
Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
This project will also include replacement of the Storm Sewer main across Country Club Drive, through
the Marshall Golf Course to the outfall into the Redwood River.
Latest Update:
March 29th, 2021 - City staff and the contractor will be scheduling a kick off meeting
with utilities and adjacent residents along these routes in May.


Project Z80
T.H. 23/Independence Park Sewer Realignment Project
Expected Advertisement: April 2021     -     Prime Contractor: TBD
Construction Begin: June 2021 (anticipated)      -     Anticipated Completion: October 2021
Project Details: Construction of Sanitary Sewer and Storm Water improvements adjacent to Highway
23 including relocation of Sanitary Sewer to Nwakama Street and
other miscellaneous work.
Latest Update: March 29th, 2021 - Project plans are in development. Advertisement is expected in April. 

Project Z51
2021 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date:
February 23rd, 2021     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 2021 (anticipated)     -     Anticipated Completion: September 2021
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: March 29th, 2021 - City staff has contacted the contractor to discuss project
start date and timeline.

Click Here to download the Project Z51 Newsletter

Project Z88
2021 State Aid Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date:
April 13th, 2021     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 2021 (anticipated)     -     Anticipated Completion: September 2022
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: April 14th, 2021 - Duininck, Inc. was awarded the contract at the 4/13 Council
meeting. Staff will be coordinating with the contractor on project timeline and details.

Click Here to download the Project Z88 Newsletter


Project Z50
2021 Bituminous Chip Sealing Project
Bid Award Date: March 9th, 2021     -     Prime Contractor: Asphalt Preservation Company Inc., Detroit Lakes, MN
Construction Begin: June 1st, 2021 (anticipated)     -     Anticipated Completion: September 2021
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: April 12th, 2021 - Asphalt Preservation has identified June 1st as a desired start date for the chip
seal work in Marshall, weather permitting. Updates will be posted when available.

Project Z78
Storm Structure Outfall Improvements Project
Bid Award Date:
April 13th, 2021     -     Prime Contractor: R & G Construction Co., Marshall, MN
Construction Begin: July 2021 (anticipated)     -     Anticipated Completion: October 2021
Project Details: Installation of two storm sewer manholes adjacent to Saratoga Street and the
Redwood River Diversion Channel. 
Latest Update: April 14th, 2021 - R & G Construction Co. was awarded the contract at the 4/13 Council
meeting. Staff will be coordinating with the contractor on project timeline and details.

MERIT Center Pond Outfall Improvements
Bid Award Date: September 8th, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: April 2021     -     Anticipated Completion: July 2021
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.
Latest Update: March 29th, 2021 - A coordination meeting with MERIT Center staff, utilities, City
staff and the contractor will take place next week. The contractor is expecting to begin installing
storm sewer pipe beginning next week.