Construction Projects

Construction Projects


Project ST-003
S. 1st St./Greeley St./Williams St. Reconstruction Project
Project Award: February 8, 2022     -     Prime Contractor: R&G Construction, Marshall, MN
Construction Begin:
July 2022      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of S. 1st Street between George St. and Greeley St., Greeley Street
between W. College Dr. and Saratoga St., and Williams Street between George St. and Maple St. Work
will include replacement of Sanitary Sewer, Watermain, Storm Sewer Catch Basins, Grading, Curb and
Gutter, Sidewalk, Asphalt Paving and other miscellaneous work. 
Latest Update:
July 25th, 2022 - R&G has placed new watermain and sanitary sewer main on S. 1st St. from
DeSchepper to George Streets. They are currently installing private services from the mains. Once these two
blocks have been completed, it is anticipated that underground utility work will continue on Greeley St.
During underground utility placement, access will be restricted in the areas of work. Please plan to park in
alternative locations when able. No thru traffic will be allowed in the construction area during the project.
Please utilize alternative routes during construction.
Click Here to View the Informational Meeting Powerpoint Presentation
Click Here to View the Project's StoryMap that includes information regarding the project.
Click Here to Provide Comments about the project.

Project ST-004
Halbur Road Reconstruction Project
Project Award: February 22, 2022     -     Prime Contractor: Duininck, Inc., Prinsburg, MN
Construction Begin:
June 2022      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of Halbur Road between Michigan Ave. and Erie Rd. (Co. Rd. 33). Work
will include replacement of Sanitary Sewer, Storm Sewer Catch Basins, Grading, Curb and Gutter,
Sidewalk, Concrete Paving and other miscellaneous work. 
Latest Update:
July 25th, 2022 - Duininck has completed underground utility replacements and placement
of gravel base on the project. The contractor is currently preparing to set up for curb and gutter pouring when
schedules permit. No traffic will be allowed on Halbur Road during construction. During this time, properties
along Halbur Road will have alternative means of access from Erie Road or Michigan Avenue. Please utilize
these alternative accesses during construction. 
Click Here
to View Recent Photos
Click Here
to View the Pre-Construction Meeting Notes

Click Here
to View the Informational Meeting Powerpoint Presentation
Click Here to View the Project's StoryMap that includes information regarding the project.
Click Here to Provide Comments about the project.

Project ST-005
Rose Parking Lot Reconstruction Project
Project Award: May 24, 2022     -     Prime Contractor: R&G Construction Co., Marshall, MN
Construction Begin:
June 8, 2022      -     Construction Completion: June 24, 2022
Project Details:
Reconstruction of the Rose downtown city parking lot adjacent to W.
Lyon Street. Work will include Grading, Curb and Gutter, Sidewalk, Concrete Paving and other
miscellaneous work. 
Latest Update:
June 29, 2022 - R&G Construction has completed work on this parking lot and the
lot is opened for public use. 

Project ST-006
Safe Routes to School (SRTS) School Pedestrian Crossing Improvements Project
Project Award: May 11, 2022     -     Prime Contractor: Duininck, Inc., Prinsburg, MN
Construction Begin:
July 2022 (anticipated)      -     Anticipated Completion: August 2022
Project Details:
Construction of pedestrian crossing enhancements and associated signage. Work will
include construction of ADA-compliant pedestrian ramps and sidewalk, raised pedestrian refuge islands,
installation of Rectangular Rapid Flashing Beacon (RRFB) signage, Dynamic Speed Feedback & School
Zone Speed Limit signage and other miscellaneous work. This project is mainly funded through a grant
received from MnDOT.
Latest Update:
July 25th, 2022 - Duininck is anticipating beginning work on this project within the next
couple weeks beginning with removal of the center median pavement, sidewalk and curb ramp areas.
Due to supply chain delays, installation of the enhanced signage may be delayed until October.

Project ST-007
2022 UCAP Bus Shelter Construction Project
Expected Advertisement: June 2022     -     Prime Contractor: TBD
Construction Begin:
August 2022 (anticipated)      -     Anticipated Completion: September 2023
Project Details:
Construction and installation of several bus stop shelter pads and structures located
at various UCAP-operated bus shelter locations throughout the City of Marshall. Work will include
Grading, Curb and Gutter, Sidewalk, Concrete Paving, Bus Shelter Foundation and Assembly, and other
miscellaneous work. This project is mainly funded through a grant received by UCAP from MnDOT.
Latest Update:
December 22th, 2021 - Engineering staff is currently developing plans for this project. 

Project ST-023
W. Lyon Street (College to 1st) Reconstruction Project
Project Award: May 24, 2022     -     Prime Contractor: R&G Construction Co., Marshall, MN
Construction Begin:
July 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Reconstruction of W. Lyon Street between College Dr. and N. 1st St. Work
will include replacement of Sanitary Sewer, Watermain, Grading, Curb and Gutter, Sidewalk,
Concrete Paving and other miscellaneous work. 
Latest Update:
July 25th, 2022 - R&G is currently placing new curb along the project. Concrete
street paving is anticipated to follow shortly afterwards. Traffic will not be able to access this
block of Lyon Street during construction. Please utilize alternative routes during construction.
 

Project ST-024
Baldwin Parking Lot Reconstruction Project
Project Award: July 12, 2022     -     Prime Contractor: R&G Construction Co. 
Construction Begin:
August 2022 (anticipated)      -     Anticipated Completion: June 2023
Project Details:
Reconstruction of the Baldwin downtown city parking lot adjacent to W.
Lyon Street. Work will include Grading, Concrete Paving and other miscellaneous work. 
Latest Update:
July 25th, 2022 - R&G is expecting to begin this work in the next couple weeks,
schedules and weather permitting. Work is expected to take two weeks to complete. Please
utilize nearby on-street parking during construction.

Project SWM-002
Legion Field Stormwater Improvements (Phase II) Project - Parkway Basin
Expected Advertisement: June 2022     -     Prime Contractor: TBD
Construction Begin:
July 2022 (anticipated)      -     Anticipated Completion: October 2023
Project Details:
Reconstruction of S. 1st Street between George St. and Greeley St., Greeley Street
between W. College Dr. and Saratoga St., and Williams Street between George St. and Maple St. Work
will include replacement of Sanitary Sewer, Watermain, Storm Sewer Catch Basins, Grading, Curb and
Gutter, Sidewalk, Asphalt Paving and other miscellaneous work. 
Latest Update:
December 22th, 2021 - Bolton & Menk is assisting City Engineering staff on developing
plans for this project. 


Project PK-001
Independence Park Trail Replacement Project
Bid Award Date:
August 25th, 2021     -     Prime Contractor: A & C Excavating, Marshall, MN
Construction Begin: September 16, 2021     -     Anticipated Completion: July, 2022
Project Details: Replacement of the existing trails throughout Independence Park including
the area around the baseball field area.

Latest Update: July 25th, 2022 - A&C Excavating has completed trail paving on this project. The contractor
is finishing grading topsoil and finishing work to prepare for seeding. Seeding is expected to occur when
weather conditions are better for growth. 

Click Here to see recent construction photos.


Project SWM-007
Independence Park Pond Forebay Expansion Project
Bid Award Date:
October 18th, 2021     -     Prime Contractor: Towne & Country Excavating, Garvin, MN
Construction Begin: April 2022     -     Anticipated Completion: July, 2022
Project Details: Excavation and expansion of the pond forebay at the south end of Independence
Park including pipe culvert and new concrete trail. 

Latest Update: June 29, 2022 - Towne & Country Excavating has completed work on this project. 
Click Here to see recent construction photos.

Project Z87
Diversion Channel Slope Repair and Sheet Pile Removal Project
Bid Award Date:
September 14th, 2021     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: June 27, 2022     -     Completion: October 2022
Project Details: Grading and slope correction of washout areas of the Redwood River Diversion
Channel. Also includes removal of sheet piling and storm water outfall repairs. 

Latest Update: July 11th, 2022 - R&G has completed construction on the project. 

Project ST-002-2022
2022 Bituminous Overlay and Pedestrian Ramp Improvements Project
Project Award:
February 8, 2022     -     Prime Contractor: Duininck, Inc., Prinsburg, MN
Construction Begin:
July 2022 (anticipated)      -     Anticipated Completion: September 2022
Project Details:
Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.  

Latest Update:
July 25, 2022 - Duininck has milled all the streets on this project. Paving is expected
to begin on Wednesday, weather permitting. On-street parking will continue to be restricted until
new pavement is placed. New pavement will be inaccessible for a short period to allow for proper
cooling before ready for traffic.
Click Here to view a map of the routes.

Project ST-001-2022

2022 Bituminous Chip Sealing Project
Project Award: February 22, 2022     -     Prime Contractor: Pearson Bros., Inc., Hanover, MN
Construction Begin:
August 2022 (anticipated)      -     Anticipated Completion: August 2022
Project Details:
Chip sealing on city streets at various locations within the City of Marshall. 
Latest Update:
March 23, 2022 - This project was awarded to Pearson Bros., Inc. of Hanover.
Engineering staff will be meeting with the contractor to discuss project details and schedule. 
Click Here to view a map of the routes.