Construction Projects

Construction Projects


Project Z75 / S.A.P. # 139-124-004
South 4th Street Reconstruction - Elaine Avenue to Country Club Drive
Bid Award Date: April 14th, 2020     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: Week of July 6th, 2020      -     Anticipated Completion: November 2020
Project Details: Reconstruction of South 4th Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk, Bike Path, Asphalt Paving and other
miscellaneous work.
Latest Update: July 31st, 2020 - R & G has completed sanitary sewer and water main construction
between Country Club Drive and James Avenue. Contractor will complete the services in this area
over the next couple days. MMU is coordinating with other private utilities on relocation of facilities
at the intersection of S. 4th Street and James Avenue. Work will continue over the next couple weeks
with storm sewer construction down to James Avenue and underground work between James Avenue
and Southview Drive. During construction, S. 4th Street will be closed to thru traffic. Only local traffic
will be allowed access. Please plan an alternate route and expect some traffic delays in the area.


Project Z76
South 1st Street Reconstruction - Southview Drive to north of George Street
Bid Award Date: May 26th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: September 2020 (anticipated)      -     Anticipated Completion: November 2020
Project Details: Reconstruction of South 1st Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
Latest Update: May 29th, 2020 - Project has been awarded to the lowest bidder, Duininck, Inc.
City staff will be scheduling a meeting with the Contractor to discuss schedule and other project
related items. During construction, S. 1st Street will be closed to thru traffic. Only local traffic
will be allowed access. Please plan an alternate route and expect some traffic delays in the area.


Project Z52 / S.P. # 139-090-005
UCAP Bus Shelters and ADA Improvements - Birch Street, South 4th Street and North 4th Street
Bid Award Date: August 23rd, 2019     -     Prime Contractor: Hisken Construction, Marshall, MN
Construction Begin: May 18th, 2020      -     Anticipated Completion: July 3rd, 2020
Project Details: Construction of Sidewalk, Curb and Gutter, Bus Stop Shelter Foundations, ADA
Improvements and other miscellaneous work.
Latest Update: July 31st, 2020 - Work on this project has been completed including installation of
the new bus shelters at all three locations.


Click Here to See Recent Photos

Project Z51
2020 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date: 
March 24th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 2020 (anticipated)     -     Anticipated Completion: September 2020
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: July 31st, 2020 - The Contractor has completed the work for this contract.
All ADA pedestrian ramp work has been completed including re-seeding disturbed areas.


Click Here to See Recent Photos

Project Z50
2020 Bituminous Chip Sealing Project
Bid Award Date: March 24th, 2020     -     Prime Contractor: Pearson Bros., Inc., Hanover, MN
Construction Begin: August 17th, 2020 (anticipated)     -     Anticipated Completion: September 2020
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: July 31st, 2020 - Project has been awarded. Pearson Bros. anticipates a start date
of August 17th. Construction should last 2-3 days, weather permitting. Expect slight traffic impacts
and isolated street 
closures during construction. During chip sealing, oil & loose rock may be
present on the roadway. 
Please be aware of traffic controls and closures to avoid vehicle damage
during construction.

Click Here to download the Project Flyer

Project Z77
Storm Water Pond Improvements
Bid Award Date: June 23rd, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: August 2020 (anticipated)     -     Anticipated Completion: October 2020
Project Details: Improvements on the stormwater ponds adjacent to Legion Field Road.
Latest Update: June 30th, 2020 - Project has been awarded to the lowest bidder, Towne & Country
LLC of Garvin, Minnesota. 
City staff will be scheduling a meeting with the Contractor to discuss
schedule and other project related items. During construction, there will be impacts to the accessibility
of the ball fields adjacent to Legion Field Road. During culvert installation, Legion Field Road will be
closed temporarily. During that time, please plan an alternate route and expect some traffic delays
in the area.


MERIT Center Pond Outfall Improvements
Bid Award Date: September 2020 (anticipated)     -     Prime Contractor: TBD
Construction Begin: September 2020 (anticipated)     -     Anticipated Completion: October 2020
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.

Latest Update: May 4th, 2020 - Project is currently in development.