Construction Projects

Construction Projects


Project Z82
N. 1st St./W. Redwood St./W. Marshall St. Reconstruction Project
Bid Award Date: February 9th, 2021     -     Prime Contractor: D & G Excavating, Inc., Marshall, MN
Construction Begin: April 26, 2021      -     Anticipated Completion: September 2021
Project Details: Reconstruction of N. 1st Street from E. Main St. to W. Marshall St., W. Redwood Street
from N. 1st St. to E. College Dr. and W. Marshall Street from N. 1st St. to E. College Dr. Work will
include replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk,
Asphalt Paving and other
miscellaneous work.
Latest Update: July 28th, 2021 - D&G has completed installation of the watermain, sanitary, and storm sewer
main on the project. Currently, the contractor is installing curb, driveways, and sidewalk on 1st Street. Accesses
along the new curb will be restricted to allow the concrete to reach the needed strength to carry vehicles. The
bridge adjacent to Main Street will be closed to all traffic until final paving is completed. Please use an alternative
route to access residences and businesses in the area. Local traffic only will be allowed in the project area. Please
plan an alternative route during this time.

Click Here to view some project photos
Click Here to download the Project Z82 Newsletter
Click Here to download the Project Z82 Pre-Construction Meeting Notes from 4/21/2021

Project Z83
James Ave./Camden Dr. Reconstruction Project
Bid Award Date: February 23rd, 2021     -     Prime Contractor: Kuechle Underground, Inc., Kimball, MN
Construction Begin: May 24th, 2021      -     Anticipated Completion: September 2021
Project Details: Reconstruction of James Avenue between S. 4th St. and Camden Dr. and Camden Drive
between James Ave. and S. 4th St. Work will include replacement of Sanitary Sewer,
Watermain, Storm
Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
This project will also include replacement of the Storm Sewer main across Country Club Drive, through
the Marshall Golf Course to the outfall into the Redwood River.
Latest Update:
July 28th, 2021 - Kuechle Underground has completed underground utility work on the 
project. The contractor has installed the gravel base on Camden Drive and James Avenue. Curb and gutter
is planned to be installed this week. When curb and gutter is placed, access to driveways will be restricted
until the necessary cure time has passed to allow the concrete to achieve the needed strength to carry
vehicles. Local traffic only will be allowed in the project area. Please plan an alternative route during this time.

Click Here to view some project photos
Click Here to download the Project Z83 Newsletter


Project Z80
T.H. 23/Independence Park Sewer Realignment Project
Expected Advertisement: May 2021     -     Prime Contractor: D&G Excavating, Marshall, MN
Construction Begin: August 2021 (anticipated)      -     Anticipated Completion: October 2021
Project Details: Construction of Sanitary Sewer and Storm Water improvements adjacent to Highway
23 including relocation of Sanitary Sewer to Nwakama Street and
other miscellaneous work.
Latest Update: July 28th, 2021 - D & G is planning to start around August 1st. The contractor is expected
to start with sewer replacement on Nwakama Street and Baseline Road. Notices will be sent out when
street closures will occur. Please find an alternative route during construction.


Project Z51
2021 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date:
February 23rd, 2021     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 3rd, 2021     -     Completion: June 17th, 2021
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: July 1st, 2021 - Duininck has completed the construction on this project. Some
turf re-establishment remains before this project will be closed.

Click Here to view some project photos
Click Here to download the Project Z51 Newsletter

Project Z88
2021 State Aid Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date:
April 13th, 2021     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: June 14th, 2021      -     Anticipated Completion: August 2021
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: July 28th, 2021 - Duininck is continuing construction on pedestrian ramp replacements
this week on Southview Drive, followed by 4th, 6th, and Marshall Streets. If you have landscaping or
irrigation in the area of a pedestrian ramp on these routes, please make arrangements to mark or
relocate those items to prevent damage. Milling is anticipated to continue during the week of August
16th, weather and schedule permitting. Overlay paving would be expected shortly afterwards. 

Click Here to view some project photos
Click Here to download the Project Z88 Newsletter


Project Z50
2021 Bituminous Chip Sealing Project
Bid Award Date: March 9th, 2021     -     Prime Contractor: Asphalt Preservation Company Inc., Detroit Lakes, MN
Construction Begin: June 8th, 2021     -     Completion: June 14th, 2021
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: June 21st, 2021 - Asphalt Preservation has completed the work on this project.

Project Z78
Storm Structure Outfall Improvements Project
Bid Award Date:
April 13th, 2021     -     Prime Contractor: R & G Construction Co., Marshall, MN
Construction Begin: May 2021     -     Completion: May 18th, 2021
Project Details: Installation of two storm sewer manholes adjacent to Saratoga Street and the
Redwood River Diversion Channel. 
Latest Update: May 19th, 2021 - R & G Construction has completed the installation of the two
manholes on this project.

MERIT Center Pond Outfall Improvements
Bid Award Date: September 8th, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: April 2021     -     Completion: May 7th, 2021
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.
Latest Update: May 12th, 2021 - Towne & Country has completed the work on this project.