Construction Projects

Construction Projects


Project Z75 / S.A.P. # 139-124-004
South 4th Street Reconstruction - Elaine Avenue to Country Club Drive
Bid Award Date: April 14th, 2020     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: Week of July 6th, 2020      -     End of 2020 Construction: November 23rd, 2020
Project Details: Reconstruction of South 4th Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk, Bike Path, Asphalt Paving and other
miscellaneous work.
Latest Update: November 24th, 2020 - R & G has completed paving construction and topsoil/mulch
on this project. The contractor is planning to return in 2021 to complete seeding the new turf along
the entire project.


Click Here to See Recent Photos

Project Z76
South 1st Street Reconstruction - Southview Drive to north of George Street
Bid Award Date: May 26th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: September 17th, 2020      -     End of 2020 Construction: November 23rd, 2020
Project Details: Reconstruction of South 1st Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
Latest Update: November 24th, 2020 - Duininck has completed all utility and street construction on this 
project. The contractor has also placed a temporary mulch to prevent topsoil erosion for the winter.
Duininck will return in 2021 to construct the remaining sidewalk that was not able to be constructed this
year due to cold temperatures. After sidewalk construction, the contractor will complete permanent
seeding for the new turf along the entire project.


Click Here to download the Project Flyer

Project Z52 / S.P. # 139-090-005
UCAP Bus Shelters and ADA Improvements - Birch Street, South 4th Street and North 4th Street
Bid Award Date: August 23rd, 2019     -     Prime Contractor: Hisken Construction, Marshall, MN
Construction Begin: May 18th, 2020      -     Completion: July 2nd, 2020
Project Details: Construction of Sidewalk, Curb and Gutter, Bus Stop Shelter Foundations, ADA
Improvements and other miscellaneous work.
Latest Update: July 31st, 2020 - Work on this project has been completed including installation of
the new bus shelters at all three locations.


Click Here to See Recent Photos

Project Z51
2020 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date: 
March 24th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 26th, 2020     -     Completion: June 16th, 2020
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: July 31st, 2020 - The Contractor has completed the work for this contract.
All ADA pedestrian ramp work has been completed including re-seeding disturbed areas.


Click Here to See Recent Photos

Project Z50
2020 Bituminous Chip Sealing Project
Bid Award Date: March 24th, 2020     -     Prime Contractor: Pearson Bros., Inc., Hanover, MN
Construction Begin: August 17th, 2020     -     Completion: September 14th, 2020
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: September 14th, 2020 - The contractor has completed the work for this contract.

Click Here to download the Project Flyer

Project Z77
Storm Water Pond Improvements
Bid Award Date: June 23rd, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: September 14h, 2020     -     Anticipated Completion: October 2020
Project Details: Improvements on the stormwater ponds adjacent to Legion Field Road.
Latest Update: November 2nd, 2020 - The contractor has completed the work for this contract.

Click Here to download the Project Flyer

Click Here to See Recent Photos


MERIT Center Pond Outfall Improvements
Bid Award Date: September 8th, 2020     -     Prime Contractor: Towne & Country Excavating LLC, Garvin, MN
Construction Begin: April 2021 (anticipated)     -     Anticipated Completion: July 2021
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.
Latest Update: November 2nd, 2020 - The City Council has awarded this contract to Towne &
Country Excavating LLC of Garvin, MN. The contractor is expected to begin work in 2021.