Construction Projects

Construction Projects


Project Z75 / S.A.P. # 139-124-004
South 4th Street Reconstruction - Elaine Avenue to Country Club Drive
Bid Award Date: April 14th, 2020     -     Prime Contractor: R & G Construction, Marshall, MN
Construction Begin: May 2020 (anticipated)      -     Anticipated Completion: November 2020
Project Details: Reconstruction of South 4th Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer, Grading, Curb and Gutter, Sidewalk, Bike Path, Asphalt Paving and other
miscellaneous work.
Latest Update: May 29th, 2020 - City staff has met with the Contractor to discuss the project.
Currently, Arvig is in the process of relocating Great Plains Natural Gas mains and services. This
work will continue until approximately mid-to-late June. During this time, please use caution around
vehicles, workers and excavated areas. The Contractor is expected to begin excavation of the roadway
in early July. During construction, S. 4th Street will be closed to thru traffic. Only local traffic will
be allowed access. Please plan an alternate route and expect some traffic delays in the area.


Project Z76
South 1st Street Reconstruction - Southview Drive to north of George Street
Bid Award Date: May 26th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: July 2020 (anticipated)      -     Anticipated Completion: November 2020
Project Details: Reconstruction of South 1st Street including replacement of Sanitary Sewer,
Watermain, Storm Sewer Catch Basins, Grading, Curb and Gutter, Sidewalk, Asphalt Paving and
other miscellaneous work.
Latest Update: May 29th, 2020 - Project has been awarded to the lowest bidder, Duininck, Inc.
City staff will be scheduling a meeting with the Contractor to discuss schedule and other project
related items. During construction, S. 1st Street will be closed to thru traffic. Only local traffic
will be allowed access. Please plan an alternate route and expect some traffic delays in the area.


Project Z52 / S.P. # 139-090-005
UCAP Bus Shelters and ADA Improvements - Birch Street, South 4th Street and North 4th Street
Bid Award Date: August 23rd, 2019     -     Prime Contractor: Hisken Construction, Marshall, MN
Construction Begin: May 18th, 2020      -     Anticipated Completion: July 2020
Project Details: Construction of Sidewalk, Curb and Gutter, Bus Stop Shelter Foundations, ADA
Improvements and other miscellaneous work.
Latest Update: May 29th, 2020 - Contractor has begun sidewalk and pedestrian ramp construction
along the Birch Street section of the project. Additional concrete work is expected through the next
week. After Birch Street is complete, the Contractor will be proceeding either the S. 4th St. or
N. 4th St. portions of the project. Isolated lane and sidewalk closures should be expected during
construction.


Project Z51
2020 Bituminous Overlay and Pedestrian Ramp Improvements Project
Bid Award Date: 
March 24th, 2020     -     Prime Contractor: Duininck, Inc., Marshall, MN
Construction Begin: May 2020 (anticipated)     -     Anticipated Completion: September 2020
Project Details: Construction of Asphalt Overlays and Pedestrian Ramp Improvements on city
streets at various locations within the City of Marshall.

Latest Update: May 29th, 2020 - The Contractor has begun curb and gutter and pedestrian ramp
replacements along Paris Road. Additional pedestrian ramp replacements will continue through
the next couple weeks. Roadway milling and asphalt paving is expected in mid-to-late June.
Expect slight traffic impacts and isolated street/sidewalk 
closures during construction.

Project Z50
2020 Bituminous Chip Sealing Project
Bid Award Date: March 24th, 2020     -     Prime Contractor: Pearson Bros., Inc., Hanover, MN
Construction Begin: August 2020 (anticipated)     -     Anticipated Completion: September 2020
Project Details: Chip sealing on city streets at various locations within the City of Marshall.
Latest Update: May 1st, 2020 - Project has been awarded. City staff will coordinate with the
Contractor on an approximate start date. Expect slight traffic impacts and isolated street
closures during construction. During chip sealing, oil & loose rock may be present on the roadway.
Please be aware of traffic controls and closures to avoid vehicle damage during construction.

Project Z77
Storm Water Pond Improvements
Bid Award Date: June 2020 (anticipated)     -     Prime Contractor: TBD
Construction Begin: July 2020 (anticipated)     -     Anticipated Completion: October 2020
Project Details: Improvements on the stormwater ponds adjacent to Legion Field Road.
Latest Update: May 29th, 2020 - Project is currently being advertised for bids. Award of bid
is anticipated at the Council meeting on June 23rd.

MERIT Center Pond Outfall Improvements
Bid Award Date: July 2020 (anticipated)     -     Prime Contractor: TBD
Construction Begin: July 2020 (anticipated)     -     Anticipated Completion: October 2020
Project Details: Improvements on the drainage and stormwater pond located at the MERIT
Center Driving Track.

Latest Update: May 4th, 2020 - Project is currently in development.