Closure of N. 3rd St. 4/24

Closure of N. 3rd St. 4/24
CLOSURE OF NORTH 3RD STREET BEGINNING MONDAY, APRIL 24th
R and G Construction Co. is anticipated to begin work on N 3rd Street between W Main Street and W Redwood Street on Monday, April 24, 2023.

- N 3rd Steet will be closed to all vehicular access from W Main Street to W Redwood Street.
- W Lyon Street will remain open during this time, though the intersection of W Lyon Street and N 3rd Street will be closed.
- The first week will include removal of the roadway pavement (no sidewalk removal).
- Pedestrian access to N 3rd Street will be maintained to the maximum extent practicable while utility work is occurring in this area.
- Downtown patrons may park in all City-owned parking lots (Addison, Baldwin, Rose) and on W Lyon Street.
- Sidewalks and alleys should be generally passable for customers to access businesses on N 3rd Street. The sidewalks will remain open to the maximum extent practicable while utility work is occurring.
- Access to the Post Office blue drop boxes must come from N 4th Street through the alley. Post Office drop box users can proceed down the alley to E College Drive to exit.

This first phase of construction may last into July. We ask for patience during the replacement of necessary city utilities and installation of a new concrete street and sidewalk surface in this area.

Construction updates will also be posted on the City of Marshall website. If you should have any questions, please do not hesitate to call the City of Marshall Public Works office at 507-537-6773.